You can generate your own electricity from renewable energy to offset your individual usage each month. We install one meter capable of measuring energy you consume as well as measuring the amount of net generation outflow energy you produce. If you generate more than what you need, you’ll receive utility bill credits that can be applied to reduce your bill in the amount of 125% of market priced power for all excess distributed generation.
We offer options for customers wanting to install renewable energy sources to their homes and businesses. However, we are not affiliated with any developers that may offer incentives or pricing options.
Because NIPSCO is not affiliated with developers, it is important to educate yourself on all program offerings and carefully review proposals and contracts to determine if they are the best fit for you.
Program details
- Must be an existing electric customer
- Must be owned by the customer
- Must be wind, solar or hydroelectric projects
- DG Billing Credits are applied to your bill
- Supports distributed generation projects sized at a nameplate capacity of the less than one (1) megawatt or the customer's average annual consumption of electricity on the premises
- Interconnection and Net Metering agreement are required
- You’re responsible for infrastructure upgrades and installation costs
- You’re responsible for maintenance of the generating device and interconnection wiring
- Customer must abide by the applicable NIPSCO Electric Tariff(s) and Agreements
Install or connect your equipment
The following information will help you with the interconnection process. The level and type of interconnection will vary with the type of customer and the size of the generator.
Research
Research the interconnection process to understand all requirements (including potential municipal restrictions, building and zoning requirements, insurance requirements, safety regulations, application fees, installation, electrical requirements and more).
- Excess Distributed Generation Standard - Requirements and guidelines for interconnection of customer owned, Distributed Resource (DR) generation source, to NIPSCO’s electric system.
- Rider 579 - Interconnection Standards – Information about interconnection requirements, fees and standards.
- Rider 589 - Excess Distributed Generation Tariff - Rate schedules and other information regarding requirements.
- Indiana Administrative Code Rule 4 - Instructions for cogeneration and alternate energy production facilities.
Steps to Excess Distributed Generation Connection
Step 1: Submit Application
Email completed applications to CNB@nisource.com or mail printed applications to 801 E. 86th Avenue, Attention: New Business, Merrillville, IN 46410. Please also include a signed copy of the New Applicant DG Customer Letter along with the completed application.
There is no application fee for Level 1.
Greater than 10 kW*
Level 2 application (>10 kW to 2 MW) has a non-refundable fee of $50.00 and $1.00 per kW and must be submitted with the application. Level 3 application (>2 MW) has a non-refundable fee of $100 and $2 per kW and must be submitted with the applications.
If you prefer to pay the Level 2 or Level 3 application fee online or by phone, please include your preference when you submit your application to CNB@nisource.com.
* Interconnection capacities greater than 500 kW require a Direct Transfer Trip Scheme and communication equipment at the customer site and utility substation. Interconnection costs for such installations begin at $125,000.
Step 2: Technical Review
Our team will review your application and provide you with next steps. A technical review will be conducted to determine if the project can move forward or if an additional study will be needed to determine the impact to the broader electric distribution system. This additional study may be required before receiving approvals and starting construction. We will notify you once your application is approved.
Step 3: Agreements
You will be required to sign any applicable agreements. Project construction may begin when all agreements are complete. A new meter is installed once installation is complete per NIPSCO standards.